The Public Utility Commission of Texas (PUCT) on Thursday approved the Electric Reliability Council of Texas' (ERCOT) first 'Batch Zero' process for large electricity users, creating a new framework to manage surging grid connection requests from data centers and other high-demand customers.
The process will group qualified projects of 75 megawatts (MW) or more into a single study, allowing ERCOT to assess future demand, allocate available grid capacity and identify transmission upgrades. ERCOT said it is tracking more than 438,000 MW of large-load requests, nearly 89% of them from data centers.
德克萨斯州公共事业委员会(PUCT)周四批准了德克萨斯电力可靠性委员会(ERCOT)的首个针对大用电户的'零批次'流程,建立了新框架以管理数据中心和其他高需求客户激增的电网接入请求。
该流程将把75兆瓦(MW)及以上的合格项目归入同一批次研究,使ERCOT能够评估未来需求、分配可用电网容量并确定输电升级方案。ERCOT表示,正在跟踪超过438,000兆瓦的大负荷接入请求,其中近89%来自数据中心。